Business case & financing proposal · October 2026 ·

MAYADEEN PARK

A Seerah-themed destination fifteen minutes from the Prophet's Mosque — three revenue engines, one fixed price.

The proposition · Al-Madinah Al-Munawwarah · King Fahd ParkA proposed term facility of up to SAR 568M to Watanco Contracting Co., with security over the project to be agreedIllustrative sizingSubject to bank approval & documentationUsufruct security subject to lessor consent
SAR 550MProject cost — guaranteed maximum price, executed July 2026
SAR 499M → 2034Peak shareholder funding, repaid from project cash
Scroll
Watanco
Watanco Contracting Co.64% · funding partner, borrower & EPCF contractor
Koushan
Koushan Real Estate Development36% · developer, land rights & asset manager
Prepared by Koushan for Watanco and its financing banks
Chapter 02 · Why Madinah, why this site

A deep, growing, under-served visitor market — and a 245,337 sqm site inside the city's park.

01 · THE MARKET

Visitors stay several nights — and have little to do beyond the Haram.

Modern cultural and family experiences are scarce. The Guests of Allah programme is building structured itineraries; Mayadeen is designed as a stop on them, with shuttle links to the Prophet's Mosque.

75%Madinah hotel occupancy in 2025 — a three-year high
6.45MReligious visitors in Q1 2025, +10.7% y/y
13 → 25MAnnual visitors 2023 → 2030 target
SAR 17KAverage spend per pilgrim

Sources: Al-Maqr hospitality report via TradeArabia (2025); Ministry of Tourism; GASTAT; Global Muslim Travel Index; LDP Report 6.0. ROOMMarket studies

02 · THE DISTRICT

King Fahd Park — the city's largest green space, on the Jabal Ayr side of Madinah.

Fifteen minutes from the Haram by road, with arterial access on two sides and a resident catchment as well as the pilgrim flow.

03 · THE SITE

Fifteen minutes from the Haram — secured, permitted, and rented at a fraction of market.

TenureAl-Maqr (investment arm of Madinah Amanah) contract 23/007, Aug 2023; 50-year usufruct over 245,337 sqm to April 2074, handed over April 2024.Lease held in the Koushan data room · available on request
RentSAR 2.39M fixed per year + 2% of SPV revenue — under 3% of revenue; rent-free to 15 April 2028.
ValuationDar Al Qias (Mar 2024): market rent SAR 16.5M/yr — the contract rent is ~85% below market; pro-rated to the full site the saving is worth ≈ SAR 85M (NPV). PDFDar Al Qias report
PermitsDevelopment permits in place; hotel permit issued with site-wide commencement under the lease.
Phase 1 permits · grantedHotel Phase 2 construction permit · pendingAl-Maqr approval for the hotel · pending
04 · THE PLAN

One destination, three engines, delivered in two phases.

Phase 1 — the Experience Centre and the F&B & Retail Boulevard — opens Q4 2028 on a 24-month programme under way since August 2026. Phase 2, the 600-key hotel, starts in 2027 and opens mid-2029, all within the SAR 550M cap.

Explore the three engines →

Chapter 03 · The destination

Where the Seerah comes to life — three revenue engines on one site.

Select a component to see what it contributes and where its numbers come from. Map pins appear only on the architect's Phase 1 aerial; each component then opens on its own render. The hotel is a Phase 2 concept with no verified position on the Phase 1 plan.

Aerial concept render of Mayadeen Park Phase 1: the Experience Centre domes and the F&B boulevard along the water axis Experience Centre aerial concept render Boulevard concept render with visitors along the water axis Hotel concept render
Base case includes all three components

SAR 285M revenue by 2031

Centre 42% · hotel 38% · retail 21%. Three uncorrelated engines on one leasehold, one SPV and one fixed-price contract.

SAR 550MInvestment cap, incl. SAR 53M pre-opening
SAR 109MSPV NOI 2032
Q4 2028Phase 1 opens
Mid-2029Phase 2 hotel opens
Phase 1 · opens Q4 2028

Experience Centre

VR, 5D and immersive theatres retelling the Hijra and the great events of early Islam — the anchor at the end of the water axis, on ProFun's operator pro-forma and LDP's attendance.

1.20MVisitors 2031
SAR 119MRevenue 2031
26.2%Component IRR, 2040 exit
SAR 135MAllocated capex
Phase 1 · opens Q4 2028

F&B & Retail Boulevard

Open-air dining, cafés and specialty retail along a ceremonial water axis from the plaza to the Centre, on Savills' tenant mix scaled to the Phase 1 GLA.

92%Occupancy at stabilisation
SAR 59MRevenue 2031
19.9%Component IRR, 2040 exit
SAR 200MAllocated capex
Phase 2 · construction from 2027 · opens mid-2029

600-key Hotel

300 hotel keys and 300 serviced apartments for the multi-night religious stay. Concept by Watanco & ZFP; underwritten on IHG's per-key projections. Proceeds once the construction permit and Al-Maqr's approval are in hand.

SAR 662Blended ADR 2031
SAR 107MRevenue 2031
19.0%Component IRR, 2040 exit
SAR 215MAllocated capex

Hotspot positions identify the buildings visible in the ZFP render; they are not surveyed boundaries. The hotel plot is not drawn on the Phase 1 render and is shown from the Watanco & ZFP pre-concept design instead. PDFZFP concept design PDFHotel concept (preview, 9.8 MB)

Chapter 04 · What makes the economics work

Revenue builds to SAR 285M by 2031; the SPV clears SAR 109M of NOI in 2032.

Drag the year, tap or hover a bar, or switch a component off. Every series mirrors the master model and was reconciled to it by script (tools/data-validation.md).

One driver per engine

Experience Centre

Visitors × spend per visit

1.14M visitors in 2028 rising to 1.55M by 2040 on LDP's attendance forecast; SAR 92 → 121 revenue per visitor (admissions SAR 77 → 102 plus F&B, retail and photo). EBITDA margin after operator fees 28% → 42%.

1,205KVisitors 2031
SAR 99Revenue per visitor 2031

PAGEDeep-dive PDFProFun plan PDFLDP 6.0

Retail Boulevard

GLA × occupancy × rent

38,597 sqm Phase 1 GLA leasing up 50 → 70 → 92% on Savills' ramp; SAR 1,652 per occupied sqm across all income lines at stabilisation (unit rent alone ≈ SAR 979); +10% step-ups every three years from 2031. EBITDA margin 79%.

92%Stabilised occupancy
SAR 1,652Per occupied sqm, 2031

PAGEDeep-dive PDFSavills

Hotel

Keys × ADR × occupancy

600 keys at a blended ADR of SAR 662 in 2031 (SAR 850 in the four peak months, SAR 450 off-peak, +2.2% a year) and 62% blended occupancy (85% peak, 50% off-peak); RevPAR SAR 408 against IHG's SAR 398. GOP margin 44 → 47%.

SAR 408RevPAR 2031
62%Blended occupancy

PAGEDeep-dive PDFIHG FAP

Chapter 05 · How the partners and capital fit together

Follow the money: the bank lends to Watanco, Watanco funds the SPV, and the SPV's cash flows back the same way.

STEP 1 · WHO BORROWS

The bank lends to Watanco, the 64% shareholder and fixed-price contractor.

The SPV is not the borrower. The facility is sized on the cash the SPV sweeps to Watanco; the proposed security is over Watanco's shares in the SPV, the shareholder loan, the project cash flows and — subject to Al-Maqr's consent — the usufruct.

STEP 2 · WHO FUNDS THE SPV

Watanco lends the SPV every riyal of the SAR 550M cost, interest-free. Koushan contributes the land rights in kind.

Bank money never becomes SPV equity: it reaches the project only as Watanco's shareholder loan, which Watanco also delivers against as EPCF contractor at a guaranteed maximum price.

STEP 3 · WHERE CASH IS MADE

Three operating engines generate SAR 109M of SPV NOI by 2032.

After operator fees, land rent and revenue share, SPV overheads and zakat, and a SAR 10M minimum balance, everything else is available for the waterfall.

STEP 4 · HOW IT FLOWS BACK

100% of SPV cash repays Watanco until 2034; Watanco services the bank from that sweep.

No dividend, fee or other lender sits ahead of the shareholder loan inside the SPV. SAR 102–110M a year reaches Watanco in 2031–34 in the base case.

STEP 5 · THEN THE OWNERS

Only after the loan is repaid are distributions split 64 / 36.

SAR 125–178M a year in 2035–45 in the base case. See the two repayment timelines →

Explore each party

Select an entity for its role, economic rights, construction responsibilities and documentation status. Nothing is represented as executed unless it is.

Facility of up to SAR 568M (illustrative)Debt service from the cash sweep
Shareholder loan for 100% of cost100% cash sweep until repaid

Cash waterfall — in order

Operating costs, land rent, SPV overheads, zakatAl-Maqr fixed rent SAR 2.39M + 2% of revenue; overheads cover asset management — no separate Koushan fee
Minimum cash balance SAR 10MRetained in the SPV
Shareholder loan repaid in full — interest-free, senior to all equity100% of remaining cash to Watanco until the SAR 499M peak balance is cleared (2034 in the base case)
Distributions 64 / 36From 2034; SAR 125–178M a year 2035–2045 in the base case

Watanco's financing banks Term sheet stage

  • Lends to Watanco Contracting Co. — the SPV is not the borrower; the facility is sized on the SPV's cash sweep to Watanco.
  • Proposed security: pledge over SPV shares, assignment of the shareholder loan and project cash flows, and security over the Al-Maqr usufruct subject to lessor consent.
  • Illustrative terms in the model (6.5%, 4-year grace with capitalised profit, 100% cash sweep) are for sizing only; tenor, pricing, grace, currency and covenants are open.

Watanco Contracting Co. — 64% Shareholding agreedSHA / amendment in documentation

  • Provides an interest-free shareholder loan for the full SAR 550M funding need, repaid from 100% of SPV cash before any dividend.
  • EPCF contractor and construction manager under the Master EPCF Agreement (13 July 2026): SAR 550M guaranteed maximum price, 24-month programme; any overrun is funded by Watanco.
  • Madinah-based general contractor (est. 1435H); track record includes Al Seeh Plaza Hotel and municipal works in Madinah.
  • Receives SAR 102–110M a year in 2031–34 under the cash sweep; Watanco IRR 17.3% with a 2040 exit (4.2x).

PDFMaster EPCF Agreement ROOMSHA — pending execution

Mayadeen Park SPV Established under the Master EPCF Agreement

  • Holds the 50-year Al-Maqr usufruct over 245,337 sqm, the ZFP masterplan and designs, and the development and hotel permits.
  • Owns and operates the three components through operators: ProFun/Midwam pro-forma for the Centre, Savills tenant mix for retail, hotel operator to be shortlisted (IHG benchmark).
  • Koushan holds reserved matters (Art. 12); SCCA arbitration.

Koushan Real Estate Development — 36% Shareholding agreed

  • Originated the project; contributes the land rights, masterplan, designs and permits in kind. Interim value ≈ SAR 85M (Dar Al Qias rent saving pro-rated) pending a certified valuation CP.
  • Asset manager — covered within SPV overheads, no separate fee; distributions follow repayment of the shareholder loan.

PDFDar Al Qias valuation

The 64/36 shareholding and shareholder-loan treatment are agreed between the partners; the amendment to the Master EPCF Agreement (Art. 9.1, Art. 17) and the shareholders' agreement are being documented. Facility terms are illustrative and uncommitted.

Chapter 06 · The facility and the repayment story

The project carries the debt: a SAR 499M peak need, swept to zero by 2034; an illustrative SAR 568M facility repaid by 2037.

Four numbers bankers ask for — kept deliberately apart. Project cost is what is built; the shareholder loan is how the SPV is funded; the facility is what Watanco would raise against it.

Project cost · executed GMPSAR 550MGuaranteed maximum price incl. SAR 53M pre-opening — Master EPCF Agreement, Art. 15
Shareholder loan · agreed, SHA pendingSAR 499M → 2034Peak balance (2029) → fully repaid from the 100% cash sweep
Bank facility · illustrative, uncommittedSAR 568M → 2037Peak incl. SAR 69M capitalised profit → repaid under the cash sweep; 2.38x minimum interest cover (2030); 53% peak LTV on completion value
Returns · model output19.3% / 21.2%Project IRR — hold to 2074 / exit 2040 at a 10% cap; 2.1x completion value ÷ cost

Why 568 is not 550: the sizing bridge

499.3Peak shareholder-loan balance = facility amount (SAR M)
69.1Profit capitalised during the 4-year grace (SAR M)
568.4Illustrative peak facility balance (SAR M), 2029
235.7Total profit / interest over the facility life (SAR M), of which 69.1 capitalised

The SAR 550M project cost is funded by the shareholder loan; the bank facility is a separate instrument at Watanco level whose balance includes financing cost. Source: Financing Model v1.0, sheet Bank KPIs — illustrative terms only.

Credit thesis

  • Fixed-price delivery. SAR 550M GMP from the party that also funds the SPV — overruns stay with Watanco.
  • Senior to all equity. No dividend, no fee, no lender ahead of the shareholder loan inside the SPV.
  • Whole project as collateral. Shares, shareholder loan, cash flows and the usufruct (with lessor consent).
  • Three uncorrelated engines. The loan is repaid even with all revenue 20% below plan, or the Centre at LDP's lower case.

Milestones

Aug 2026Enabling works

Under way; 24-month programme under the GMP.

2027Hotel construction starts

After the construction permit and Al-Maqr approval (6–8 months).

Q4 2028Phase 1 opens

Centre and boulevard, before Ramadan 1450H.

Mid-2029Hotel opens

Peak funding need SAR 499M in 2029.

2034Shareholder loan repaid

Distributions 64/36 begin.

2037Facility repaid (illustrative)

Under a 100% cash sweep on placeholder terms.

Definitions used on this page EBITDA · NOI · yield on cost · gross revenue · facility · capitalised financing cost
Gross revenue
All operating income of the three components before any cost, fee or rent.
Component EBITDA
Component earnings after operator / management fees; before allocated land rent and SPV overheads.
SPV NOI
Component EBITDA less SPV G&A, insurance, Al-Maqr fixed rent (SAR 2.39M) and 2% revenue share; before capex, zakat and VAT recovery.
Yield on cost
Stabilised 2032 SPV NOI ÷ total uses (SAR 550M).
Shareholder loan
Interest-free funding from Watanco for 100% of the cost, repaid by a 100% cash sweep before any distribution.
Illustrative facility
A term facility to Watanco sized on the cash sweep: 6.5%, 4-year grace with capitalised profit, 100% cash sweep. Placeholder terms for sizing; not committed.
Capitalised financing cost
Profit / interest accrued during grace and added to the facility balance rather than paid in cash (SAR 69M in the illustrative sizing).
Minimum interest cover
Lowest annual ratio of cash received by Watanco from the SPV to facility profit / interest (2.38x in 2030).

Model-linked notes: facility terms (6.5%, 4-year grace with capitalised profit, 100% cash sweep) are placeholders for sizing only; tenor, pricing, grace, currency and security are to be agreed. Nothing on this page implies a committed facility or finalised security. PAGEFull sensitivities XLSXMaster model

Chapter 07 · Protection, stress cases and due diligence

The questions a credit committee will ask — and where the answer is evidenced.

Construction riskWhat if the build costs more?

SAR 550M guaranteed maximum price from Watanco, itself the 64% shareholder and funder; any overrun is funded by Watanco. A +10% overrun stress still repays the shareholder loan in 2035. Signed 13 Jul 2026

Structural subordinationWho gets paid before the loan?

Nobody inside the SPV: 100% of cash after operating costs, land rent, overheads, zakat and a SAR 10M minimum balance repays the shareholder loan before any dividend. Agreed SHA in documentation

SecurityWhat is the collateral?

Pledge over SPV shares, assignment of the shareholder loan and project cash flows, and security over the Al-Maqr usufruct. Proposed Usufruct security subject to lessor consent

LandIs the land cost sustainable?

SAR 2.39M fixed rent plus 2% of revenue — under 3% of revenue and ~85% below the Dar Al Qias market rent; rent-free to April 2028; 50-year usufruct to 2074. Lease executed Aug 2023 Written Al-Maqr confirmation of the rent-free period — CP

Market riskWhat if visitors or guests don't come?

Three engines with different drivers: hotel 38%, Centre 42%, retail 21% of 2031 revenue. The Centre's downside is LDP's own lower-margin case; the hotel's is IHG's 300-key level. Each case alone, and all revenue −20%, still repays the shareholder loan. In the model

Phase 2What if the hotel is delayed or dropped?

Phase 1 alone (retail and Centre, SAR 332M peak need) repays the shareholder loan in 2034 at a 20.4% project IRR; the hotel adds scale, NOI and exit value. Hotel construction permit and Al-Maqr approval — CP

AlignmentAre the partners paid from the same place?

Developer and contractor are paid through the same waterfall; Koushan's asset-management role is inside SPV overheads with no separate fee, and distributions follow repayment. Agreed

Compare the base case with a model-supported downside

Only cases that exist in the Sensitivity sheet are listed; no scenario is computed on this page.

All thirteen sensitivities on the financing page →

Chapter 08 · The ask

A proposed term facility of up to SAR 568M to Watanco, against a fixed-price, Phase 1-permitted, three-engine destination in Madinah.

Facility terms · illustrative, subject to bank approvalSecurity package · proposed; usufruct subject to lessor consentEPCF & GMP · executed 13 Jul 2026SHA / 64-36 amendment · in documentationHotel permit & Al-Maqr approval · CP

What the financing bank gets

  • A borrower that is also the fixed-price contractor and the 64% funder.
  • A cash sweep senior to every equity distribution inside the SPV.
  • A proposed security package over the whole project (shares, shareholder loan, cash flows, usufruct with lessor consent), on government land at ~15% of market rent.
  • 2.38x minimum interest cover and 53% peak LTV on the illustrative sizing.

Key diligence items

  • Audited financials of Watanco.
  • Independent technical adviser on the GMP and programme.
  • Legal opinion on Saudi security and the Al-Maqr usufruct.
  • Certified in-kind valuation; Al-Maqr confirmation of the rent-free period; hotel permit and approval (Phase 2); operator shortlist.

Proposed route to close

1

Indicative terms

Nov 2026

Term sheets from Watanco's financing banks: amount, tenor, pricing, grace, currency, security and covenants.

2

Due diligence

Nov–Dec 2026

Audited financials, independent technical adviser, legal opinion on security and the usufruct.

3

Conditions precedent

Dec 2026

Amendment / SHA for 64/36; certified in-kind valuation; Al-Maqr confirmations; hotel permit and approval; operator shortlist.

4

Financial close

Q1 2027

Facility agreement; first drawdown against Watanco's approved cash-flow forecast.